CORPUS CHRISTI, Texas —
UPDATE, Oct. 8, 4:30 p.m.:
Corpus Christi Water and the Lavaca-Navidad River Authority have begun returning service to the Mary Rhodes Pipeline after repairs near the O.N. Stevens Water Treatement plant river intake station.
The interior mortar coating on the section that was repaired was finished last night. CCW and LNRA complete a low-flow pump setup to get rid of any air from the pipeline.
CCW and LNRA will continue to monitor the pipeline to make sure all air is removed. ONSWTP will be receiving some partial flow from the pipeline today.
Starting tonight, the pipeline is expected to start operations at Schedule 3, 55 million gallons per day.
The Mary Rhodes Pipeline will work at Schedule 3 maximum while upgrades at the Woodsboro Pump Station are happening.
UPDATE, Oct. 7, 3:14pm:
The connection points on the existing pipeline were prepared for welding and the replacement pipe was prepared for installation and alignment. According to a press release, this stage of the work took longer than anticipated.
Officials say Corpus Christi Water is expected to fill the pipe with water to perform a hydrostatic test, which checks all welds for leaks under pressure.
If today's work goes as planned, CCW expects to gradually return the pipeline to service throughout Thursday, Oct. 8, ramping up to Schedule 3 operations of 55 million gallons per day.
UPDATE, Oct. 6, 5:49 a.m.:
The Mary Rhodes Pipeline could be fully back in use by Thursday, Oct. 8, after crews fix a leak near the O.N. Stevens Water Treatment Plant, according to a news release Corpus Christi Water sent out Monday.
Workers cut out a broken piece of pipe about 24 feet long. They planned to weld a new piece into place Monday night and keep working through the night.
If that work went as planned, crews will coat the new pipe with a protective layer of mortar today. The city plans to start slowly sending water through the pipeline again later today.
The leak came from a welded hatch that allows access to the pipe. The hatch was built when the pipeline was first constructed more than 25 years ago. The city said it was built using methods that are now out of date, and that it has been fixing problems like this along the pipeline.
ORIGINAL:
Crews have confirmed a leak on the Mary Rhodes Pipeline, a city spokesperson told KRIS 6 News. It is the second leak on the pipeline in less than two weeks.
The leak is at a weld on a manway, an access hatch for the pipe. Welders have started removing the exterior mortar at the spots where the failed pipe will be cut.
About 24 feet of pipe will be removed and replaced, according to the spokesperson. The city has not said when the pipeline will return to service.
Corpus Christi Water announced Oct. 1 that it found a potential leak while bringing the pipeline back online after two days of scheduled work, according to a city news release. During that shutdown, the Lavaca-Navidad River Authority installed backup pumps at the Lake Texana Pump Station and city contractors added two pipeline connections.
The city said the leak is near the O.N. Stevens Water Treatment Plant, across the Nueces River. Crews began removing water from the site so contractors could dig to the pipe and assess the leak.
Rain Thursday night kept a contractor from inspecting the possible leak last week, a city spokesperson told KRIS 6 News on Oct. 2.
Second leak in less than two weeks
The pipeline went offline Sept. 19 after a leak was found on a 64-inch pipe near Highway 77, just north of Refugio, KRIS 6 News reported. Crews replaced 17 feet of pipe. An active gas line in the same trench complicated the work.
That repair kept the pipeline offline for nearly a week. The new repair is about 7 feet longer.
The 101-mile pipeline carries water from Lake Texana to the O.N. Stevens plant. Since it opened in 1998, it has had at least 33 leaks or failures, KRIS 6 News has reported.
Where the water is coming from
The pipeline will stay offline until repairs are complete, according to the city. In the meantime, the region's water is coming from the western reservoirs and the Nueces Groundwater Program.
During the Refugio repair, city officials said relying on those sources would not trigger a water emergency or drops in water pressure.
Before this leak, Corpus Christi Water planned to run the pipeline at reduced pumping rates through Nov. 16 so crews could work safely on pump station upgrades. It is not clear whether the new repair will change that schedule.
For the latest local news updates, click here, or download the KRIS 6 News App.